26. In a schedule network diagram, how do you define a critical path?

user image

Abhishek Mishra

2 years ago

There will be some activities whose start and/or end times are not crucial when activity scheduling is complete. Due to dependencies, it may be possible to begin a task later than the scheduled start date. Likewise, an activity may be completed later if no other tasks are waiting for it to be finished. Floats are the name for these timers.